Skip to main content

Oakland Coliseum South Interceptor Sewer Pipeline Rehabilitation Project

South Sewer Interceptor Pipeline Rehabilitation ProjectEBMUD will be rehabilitating a portion of its South Interceptor sewer pipeline. The south interceptor at the Oakland Coliseum is a large diameter sewer pipeline, 42 inches to 63-inch, that receives sewer flow from a number of City of Oakland sewer collections and conveys the wastewater to the District's treatment plant. The 2,500 linear feet section to be rehabilitated will start at the E parking lot and end on South Coliseum Way (TEC parking lot). Please see the map for details. 

This project will require excavating 3 access pits over the interceptor pipeline. The project will also include rehabilitating four maintenance-holes in this segment of the interceptor. This rehabilitation project will address critical pipeline corrosion and reduce the risk of pipe failure.

EBMUD Innovation

Slip Lining: Less time, less construction, fewer traffic impacts.

Slip lining is a trenchless method used to rehabilitate existing pipelines with minimal excavation. In this process, a slightly smaller, prefabricated pipe is inserted into the damaged host pipe and then grouted into place. This technique restores the structural integrity of the pipeline, prevents leaks, and extends its service life. Slip lining significantly reduces construction time, costs, and surface disruption, making it a less invasive alternative to traditional pipe replacement methods.

Workplan and Schedule

Construction and rehabilitation of the Alameda Interceptor will begin in the Fall 2026 through Spring 2027. 

Work schedule

  • Monday through Friday
  • Work hours 6 p.m. to 6 a.m.
  • Some day and weekend work will be required.
  • Work hours may vary depending on project needs.
  • The schedule is subject to change.

What to expect

Construction equipment and materials will be temporarily located within the area.

  • Temporary lighting to support night work.
  • Noise from construction equipment is expected.
  • Crew may limit traffic along street, if needed.
  • Potential night work. Notices will be sent out when needed.
  • One access pit will be excavated to facilitate the insertion of the slip line pipeline to the interceptor pipe.
  • Pedestrian and emergency vehicle access will be maintained.
  • When construction is complete, all work areas will be restored to preconstruction conditions.

Contact Information

Community Affairs
Email: construction-wastewater@ebmud.com
Phone: 510-287-0140
After-hours dispatch: 800-403-2683